I want to search for...

Permit #2026020707

Permit Details

Status: FINAL

Subdivision: 2161 - RIGHT OF WAY/STREETS/PATHS
Job Phone: 563-904-3447
Location Address: 10000 RYMFIRE DR
Type: ROW - RIGHT OF WAY
Issue Date: 02/19/2026
NOC: Unknown
Applicant name: FLORIDA POWER AND LIGHT MELBOURNE
Owner: CITY OF PALM COAST

Address

160 CYPRESS POINT PKWY

PALM COAST, FL 32164

Address

SUITE B-106

PALM COAST, FL 32164

Job Description: RYMFIRE DR 84 CONCRETE STREET LIGHTS AND POLES #2024120942
Type: CN
Original Permit #: WR13497958

Contractor

FLORIDA POWER AND LIGHT MELBOURNE
Status Location Address State License Number Phone
ACTIVE

9001 ELLIS ROAD

MELBOURNE, FL 32904

MELBOURNE 563-904-3447

Inspection History

Type Request Date Result Inspector
ROW CABLE PROJECT STATUS 05/14/2026 Status Check PFLANAGAN
Note: PROJECT COMPLETED ---------------------------------------------------------------------- 6/6/2025 - PREVIOUS INSPECTION NOTES 06/06/25 TPOLACEK**** STRAW STILL REMAINS AND EROSION HAS BEGUN. CONTRACTOR MUST COVER ALL BARE EARTH WITH SOD TO AVOID EROSION INTO STORMWATER SYSTEM. 3 SEC 9.04.04 erosion and sediment control measures (best management practices) LDC.9.04.04 Prior to and during construction, the permittee shall implement and maintain all erosion and sediment control measures (best management practices) required to retain sediment on-site and to prevent violations of state water quality standards. All practices must be in accordance with Section 9.04.06. If site specific conditions require additional measures during any phase of construction or operation to prevent erosion or control sediment beyond those specified in the erosion and sediment control plan, the permittee shall implement additional best management practices as necessary, in accordance with Section 9.04.06. The permittee shall correct any erosion or shoaling that causes adverse impacts to the water resources. 06/04/25 TPOLACEK*** STOPPED CREW WORKING CLOSE TO RED MILL. FOUND WORKER THROWING SEED AND STRAW IN THE ROW. ALL BARE EARTH REPAIRS MADE WITHIN THE ROW MUST BE MADE WITH SOD. INSPECTOR EXLAINED THAT ALL AREAS ALREADY COVERED MUST BE REMOVED. WILL CHECK BACK ON FRIDAY 06/06/25
ROW - FINAL INSPECTION 05/14/2026 APPROVED PFLANAGAN
Note: CORRECTIONS MADE ------------------------------------------------------------------------------- 2/20/2026 - PREVIOUS INSPECTION NOTES 02-20-26 TPOLACEK*** THERE ARE SEVERAL POLES AND ELECTRICAL CONNECTON BOXES WHERE THE GROUND HAS SETTLED AND IS BELOW GRADE. IN ACCORDANCE WITH COPC STANDARDS ALL BARE GROUND AROUND POLES AND BOXES MUST BE STABILIZED WITH SOD. THERE MAY NOT BE ANY SEED AND STRAW WITHIN THE ROW OR STONE BASE MATERIAL EXPOSED. LDC-Damage to private land, public rights-of-way, or other lots shall be repaired Sec. 24-163. (c) Damage to private land, public rights-of-way, or other lots shall be repaired prior to issuance of a certificate of occupancy. In case of damage to private property or to public rights-of-way, the damage must be corrected by the owner and contractor as directed by the City Manager or designee. WR13497958- INSTALL 84 CONCRETE STREET LIGHTS AND BORE/TRENCH BETWEEN POLES
ROW - FINAL INSPECTION 02/20/2026 Disapproved - NO FEE TPOLACEK
Note: 02-20-26 TPOLACEK*** THERE ARE SEVERAL POLES AND ELECTRICAL CONNECTON BOXES WHERE THE GROUND HAS SETTLED AND IS BELOW GRADE. IN ACCORDANCE WITH COPC STANDARDS ALL BARE GROUND AROUND POLES AND BOXES MUST BE STABILIZED WITH SOD. THERE MAY NOT BE ANY SEED AND STRAW WITHIN THE ROW OR STONE BASE MATERIAL EXPOSED. LDC-Damage to private land, public rights-of-way, or other lots shall be repaired Sec. 24-163. (c) Damage to private land, public rights-of-way, or other lots shall be repaired prior to issuance of a certificate of occupancy. In case of damage to private property or to public rights-of-way, the damage must be corrected by the owner and contractor as directed by the City Manager or designee. WR13497958- INSTALL 84 CONCRETE STREET LIGHTS AND BORE/TRENCH BETWEEN POLES
ROW CABLE PROJECT STATUS 06/06/2025 Disapproved -FEE REQUIRED TPOLACEK
Note: 06/06/25 TPOLACEK**** STRAW STILL REMAINS AND EROSION HAS BEGUN. CONTRACTOR MUST COVER ALL BARE EARTH WITH SOD TO AVOID EROSION INTO STORMWATER SYSTEM. 3 SEC 9.04.04 erosion and sediment control measures (best management practices) LDC.9.04.04 Prior to and during construction, the permittee shall implement and maintain all erosion and sediment control measures (best management practices) required to retain sediment on-site and to prevent violations of state water quality standards. All practices must be in accordance with Section 9.04.06. If site specific conditions require additional measures during any phase of construction or operation to prevent erosion or control sediment beyond those specified in the erosion and sediment control plan, the permittee shall implement additional best management practices as necessary, in accordance with Section 9.04.06. The permittee shall correct any erosion or shoaling that causes adverse impacts to the water resources. 06/04/25 TPOLACEK*** STOPPED CREW WORKING CLOSE TO RED MILL. FOUND WORKER THROWING SEED AND STRAW IN THE ROW. ALL BARE EARTH REPAIRS MADE WITHIN THE ROW MUST BE MADE WITH SOD. INSPECTOR EXLAINED THAT ALL AREAS ALREADY COVERED MUST BE REMOVED. WILL CHECK BACK ON FRIDAY 06/06/25
ROW CABLE PROJECT STATUS 06/04/2025 Status Check TPOLACEK
Note: 06/04/25 TPOLACEK*** STOPPED CREW WORKING CLOSE TO RED MILL. FOUND WORKER THROWING SEED AND STRAW IN THE ROW. ALL BARE EARTH REPAIRS MADE WITHIN THE ROW MUST BE MADE WITH SOD. INSPECTOR EXLAINED THAT ALL AREAS ALREADY COVERED MUST BE REMOVED. WILL CHECK BACK ON FRIDAY 06/06/25

Review History

Department Status Date In Date Out
SW1 COMPLETE 12/23/2024 12/31/2024
Note: Released By: FRANK SLADISH - (386)871-6113 - FSLADISH@PALMCOASTGOV.COM
TRENG COMPLETE 12/23/2024 12/31/2024
Note: Released By: VINEESH CRAWFORD - (386)986-3789 - VCRAWFORD@PALMCOASTGOV.COM
UD1 COMPLETE 12/23/2024 12/23/2024
Note: Released By: GREG DEGLER - (386)986-2384 - GDEGLER@PALMCOASTGOV.COM

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMINISTRATIVE RESIDENTIAL ¤30.00 02/19/2026
REINSPECTION FEE ¤40.00 02/19/2026
RSI ROW FINAL INSPECTION ¤16.25 02/19/2026
RSI SITE PLAN REVIEW ¤16.25 02/19/2026
Fees Total Due: ¤0.00 Total Paid: ¤102.50