I want to search for...
Permit #2026030134
Permit Details
Status: APPLY
| Parcel Id: 07-11-31-7028-00160-0040 |
| CONDITIONED SPACE: 1504 sqft |
| GARAGE: 396 sqft |
| OPENED PORCH (WITH ROOF) : 119 sqft |
| Total Square Footage: 2019 sqft |
| Block: 00160 |
| Subdivision: 2302 - SECTION 28-PINE GROVE |
| Job Phone: 407-476-8195 |
| Location Address: 7 POPE LN |
| Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY |
| NOC: NO DOCUMENTATION |
| Applicant name: CARLETTE RENE WITTE |
| Owner: INB BFS LAND LLC |
|
Address 7380 WEST SAND LAKE ROAD ORLANDO, FL 32819 |
|
Address SUITE 600 ORLANDO, FL 32819 |
| Lot: 0040 |
| Contracted Stated Job Value: ¤250,000.00 |
| Job Description: Single Family Residence |
| Type: CN |
Contractor
INNOVATIVE NATIONWIDE BUILDERS INC
| Status | Location Address | State License Number | Phone |
| ACTIVE |
3670 MAGUIRE BLVD #220 , |
CRC1330026 (Exp: 08/31/2026) | 855-694-6634 |
Sub Contractors
JASON LEE JAMES
| Status | Location Address | State License Number | Phone |
| ACTIVE |
217 N WESTMONTE DR SUITE 1007 ALTAMONTE SPRINGS, FL 32714 |
CAC1820196 (Exp: 08/31/2026) | 407-404-4000 |
ANTHONY OKEITH FENNELL
| Status | Location Address | State License Number | Phone |
| ACTIVE |
217 N. WESTMONTE DR, SUITE 1007 ALTAMONTE SPRINGS, FL 32714 |
EC13011194 (Exp: 08/31/2026) | 407-404-4000 |
HEATH EDWARD SANFORD
| Status | Location Address | State License Number | Phone |
| ACTIVE |
126 EAST END RD SAN MATEO, FL 32187 |
CFC1429896 (Exp: 08/31/2026) | 386-871-8823 |
TERRY BRICE DICKERSON
| Status | Location Address | State License Number | Phone |
| ACTIVE |
4300 ST JOHN'S PARKWAY ALPHARETTA, GA 30009 |
CCC1326209 (Exp: 08/31/2026) | 407-548-6733 |
Inspection History
| Type | Request Date | Result | Inspector |
| FORMBOARD SURVEY (OFFICE USE ONLY) | |||
| ENGINEERS APPROVAL LETTER (OFFICE USE) | |||
| Note: This is for welding approval | |||
| GEOTECHNICAL REPORT APPROVAL (OFFICE USE) | |||
| PLUMBING 1ST ROUGH UNDERGROUND | |||
| GRAVITY SEWER TEST | |||
| SEWER TIE IN | |||
| ELECTRIC - EARLY POWER | |||
| MONOLITHIC SLAB | |||
| LATH/BRICK/ WATER BARRIER | |||
| ALL ROUGH | |||
| WALL SHEATHING | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | |||
| ROOF VALLEY & METAL | |||
| INSULATION | |||
| DRYWALL NAILING | |||
| BLD - BUILDING FINAL | |||
| WATER METER INSTALLATION REQUEST | |||
| PEP TANK INSTALLATION REQUEST | |||
| U-CROSS CONNECTION | |||
| ROW- PRE-APRON (PRE-POUR) | |||
| ROW - FINAL APRON (AFTER POUR) | |||
| ROW - FINAL INSPECTION | |||
| U -UTILITY RESIDENTIAL FINAL |
Review History
| Department | Status | Date In | Date Out |
| BLD | HOLD | 05/28/2026 | 06/02/2026 |
| Note: Held By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM 1. Please revise Product Approval form accordingly. 2. On plan sheet S-08 under detail 29 please add comment that the welding will be inspected by engineer on record. Once inspected we ask that an Engineer's Approval Letter be submitted for it. | |||
| MECH | COMPLETE | 05/28/2026 | 06/04/2026 |
| Note: Released By: KENNETH SANDOE - - KSANDOE@PALMCOASTGOV.COM | |||
| MECH | COMPLETE | 03/10/2026 | 03/11/2026 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| BLD | COMPLETE | 03/10/2026 | 03/17/2026 |
| Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM | |||
| SWALE | COMPLETE | 03/06/2026 | 03/17/2026 |
| Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM | |||
| BLD | HOLD | 03/04/2026 | 03/09/2026 |
| Note: Held By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM Plan sheet S4 needs to be digitally signed, sealed, and verifiable. | |||
| CUSVC | COMPLETE | 03/04/2026 | 03/10/2026 |
| Note: Released By: CYNTHIA SCHWEERS - - CSCHWEERS@PALMCOASSTGOV.COM | |||
| ELEC | COMPLETE | 03/04/2026 | 03/09/2026 |
| Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM | |||
| ENGIN1 | COMPLETE | 03/04/2026 | 03/06/2026 |
| Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM | |||
| GAS | CANCEL | 03/04/2026 | 03/05/2026 |
| LOCATE | COMPLETE | 03/04/2026 | 03/04/2026 |
| Note: Released By: IVAN SANDERSON - - | |||
| MECH | HOLD | 03/04/2026 | 03/05/2026 |
| Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM State card is page with the preparers signature. Upload this page only as State Card. Use drop down menu state card and file name state card | |||
| SW1 | COMPLETE | 03/04/2026 | 03/06/2026 |
| Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM | |||
| ZON | COMPLETE | 03/04/2026 | 03/04/2026 |
| Note: Released By: CINDY CHIRI-GONCALVES - (386)986-4737 - CGONCALVES@PALMCOASTGOV.COM | |||
| BLD | PENDING |
Fees & Payments
(Permit is not ready for pickup until the permit has been processed and fees appear)
| Description | Amount Due | Date Paid |
| WATER- TURN ON | ¤50.00 | |
| ADMINISTRATIVE RESIDENTIAL | ¤30.00 | |
| INSPECTION - RESIDENTIAL | ¤805.75 | |
| PLAN REVIEW - RESIDENTIAL | ¤228.54 | |
| PLAN REVIEW - REVISION | ¤65.00 | |
| FC IMPACT FEE EMS | ¤62.00 | |
| FC IMPACT FEE LAW ENFORCEMENT | ¤218.00 | |
| FC IMPACT FEE LIBRARY | ¤268.00 | |
| FIRE RES IMPACT FEE 10-25 | ¤942.00 | |
| PEP TANK INSTALL | ¤756.74 | |
| PARKS IMPACT FEE 10-25 | ¤3,164.00 | |
| RSI DRIVEWAY AFTER POUR | ¤16.25 | |
| RSE DRIVE PRE POUR INSPECTION | ¤32.50 | |
| RSI FIELD SURVEY INSPECTION | ¤48.75 | |
| RSI FORMBOARD REVIEW | ¤16.25 | |
| RSI PLAN REVIEW NEW | ¤48.75 | |
| RSI FNL SURVEY/GRADING CERT | ¤48.75 | |
| RSI ROW FINAL INSPECTION | ¤16.25 | |
| SCHOOL BOARD IMPACT FEE RES | ¤5,450.00 | |
| WASTEWATER MAIN EXTENSION IMPA | ¤2,385.00 | |
| SURCHARGE FS 533.721 | ¤10.64 | |
| SURCHARGE - FS 468.631 | ¤15.96 | |
| SW ENG RES REVIEW 240 | ¤240.00 | |
| WATER METER W/ TAP | ¤2,326.93 | |
| TRANSP RES IMPACT FEE 10-25 | ¤5,670.08 | |
| SEWER CREDIT | (¤431.63) | |
| WASTEWATER PERM INSPECTION | ¤80.00 | |
| WASTEWATER PERM REVIEW | ¤25.00 | |
| SEWER CAPITAL FACILITY | ¤4,415.00 | |
| WATER CAPITAL FACILITY FEE | ¤3,790.49 | |
| WATER PERMIT REVIEW | ¤25.00 | |
| WATER MAIN EXTENSION IMPACT | ¤917.27 | |
| SITE PLAN 30 | ¤30.00 | |
| Fees | Total Due: ¤31,767.27 | Total Paid: ¤0.00 |