Permit #2026040874

Permit Details

Status: INSPECT

Parcel Id: 05-12-31-0650-000A0-0013
Block: 000A0
Subdivision: -
Job Phone: 706-678-2890
Location Address: 746 TOWN CENTER BLVD
Type: CSD - COMMERCIAL SITE DEVELOPMENT
Issue Date: 04/30/2026
NOC: Unknown
Applicant name: KARL CHRISTOPHER BERG JR
Owner: HP-232090 PALM COAST QOZB LLC

Address

631 W MORSE BLVD

WINTER PARK, FL 32789

Address

SUITE 200

WINTER PARK, FL 32789

Lot: 0013
Job Description: SITE WORK: POINTE GRAND AT TC - STAGE 2 BLDG 10000 G1 & G2
Type: CN

Contractor

BARNETT CONTRACTING, INC.
Status Location Address State License Number Phone
ACTIVE

PO BOX 627

WASHINGTON, GA 30673

CUC1223712 (Exp: 08/31/2026) 706-678-2890

Inspection History

Type Request Date Result Inspector
PLANNING - OFFICE USE - FINAL AS-BUILT SURVEY 05/29/2026 APPROVED DRAMIREZ
U - UTILITY COMMERCIAL FINAL 05/29/2026 FINAL APPROVED BWRIGHT
CLOSE OUT DOCUMENTS 05/28/2026 APPROVED DRAMIREZ
LDSC-IRRIGATION FINAL 05/28/2026 Disapproved - NO FEE RPICATAGI
Note: Irrigation Affidavit is not approved because: 1. Incorrect Form - Use COPC Form 2. Notary is NOT rewquired and does not add credibilty 3. Requires signature and seal from Florida RLA or Certified Irrigation Professional
UROW-SUBSTANTIAL WALK-THRU 05/26/2026 APPROVED LFITZGERALD
UROW-RETENT/DETENT STABILI 05/26/2026 APPROVED - AS NOTED JMYERS
Note: 5/26/26 BANKS ADJACENT TO 60" DONE IN ACCORDANCE WITH PENDING MODIFICATION. PIPES WITHOUT MES APPROVED PER TOWN CENTER EOR. 5/4/2026 - PREVIOUS INSPECTION NOTES 5/4/2026 - PREVIOUS INSPECTION NOTES 5/4/26 BANKS ADJACENT TO 60" PIPE ARE NOT STABILIZED ACCORDING WITH PLAN OR SWPPP. ADDED DUPLICATE- ALREADY RESULTED 5-1-26
UROW - FINAL DRAINAGE 05/26/2026 APPROVED - AS NOTED JMYERS
Note: 5/26/26 BANKS ADJACENT TO 60" DONE IN ACCORDANCE WITH PENDING MODIFICATION. PIPES WITHOUT MES APPROVED PER TOWN CENTER EOR. 5/4/2026 - PREVIOUS INSPECTION NOTES 5/4/26 MULTIPLE MES NOT INSTALLED, UNABLE TO VERIFY IF 60" PIPE UNDER ROAD IS CLEAN OF SEDIMENT, BANKS ADJACENT TO 60" PIPE ARE NOT STABILIZED ACCORDING WITH PLAN OR SWPPP.
U-ROW FINAL 05/26/2026 APPROVED - AS NOTED LFITZGERALD
Note: 5/5/2026 - PREVIOUS INSPECTION NOTES WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR TOM TO LARRY no thermo for stripping at main entrance/need to relocate light pole and hand hole LIGHT POLE/HANDHOLE JUNCTION BOX NOW RELOCATED-THERMO SCHEDULED 3 WEELS OUT-IF IT DOESN'T GET DONE THEN U-ROW FOR STAGE 3 WILL BE ON HOLD
UC-FINAL SITE INSPECTION 05/21/2026 APPROVED TPOLACEK
Note: Inspector Notes from Inspection 9602 WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR tom to larry spoke with Cooper regarding street signage indicating where certain building numbers are so emergency knows where to go
UC- PRELIMINARY AS-BUILTS 05/21/2026 APPROVED LFITZGERALD
Note: Inspector Notes from Inspection 9602 WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR tom to larry spoke with Cooper regarding street signage indicating where certain building numbers are so emergency knows where to go
UROW- PRELIMINARY AS-BUILTS 05/21/2026 APPROVED LFITZGERALD
Note: Inspector Notes from Inspection 9602 WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR tom to larry spoke with Cooper regarding street signage indicating where certain building numbers are so emergency knows where to go Randy Homes spoke with Connor-GC-and signs with building numbers with directional arrows to be installed per e-mail from Randy
UROW-RETENT/DETENT STABILI 05/05/2026 CANCELLED BY APPLICANT LFITZGERALD
Note: 5/4/2026 - PREVIOUS INSPECTION NOTES 5/4/26 BANKS ADJACENT TO 60" PIPE ARE NOT STABILIZED ACCORDING WITH PLAN OR SWPPP. ADDED DUPLICATE- ALREADY RESULTED 5-1-26
BLD - ADA RAMPS/SIDEWALKS/CROSSWALKS 05/05/2026 APPROVED HCAMACHO
BLD- ADA PARKING 05/05/2026 APPROVED HCAMACHO
BLD - ADA COMPLIANT 05/05/2026 APPROVED HCAMACHO
BLD- ADA SIGNAGECONTROL 05/05/2026 APPROVED HCAMACHO
BLD- ADA VEHICULAR WAY 05/05/2026 APPROVED HCAMACHO
BLD - ADA SIGNAGE- INFOR/DIRECT 05/05/2026 APPROVED HCAMACHO
BLD - UNDERGROUND SITE LIGHTING CONDUITS 05/05/2026 APPROVED RMARTIN
BLD - SITE LIGHTING-PLACEMENT/FOUNDATION 05/05/2026 APPROVED RMARTIN
BLD - SITE LIGHTING-POLE SET/FIXTURE 05/05/2026 APPROVED RMARTIN
UC-SUBSTANTIAL WALK-THRU 05/01/2026 APPROVED - AS NOTED LFITZGERALD
Note: WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR TOM TO LARRY several drainage deficiencies-stab slopes for 60in culvert under main thru road/couldnt detect some terminal ends/mes's for pipe outfalls/mes aprons not constructed just cut mes stick of RCP
UC- PRELIMINARY AS-BUILTS 05/01/2026 Disapproved -FEE REQUIRED LFITZGERALD
Note: WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR TOM TO LARRY as builts as explained earlier need to be on actual constrution plans-spoke with surveyor BOB to resubmit
UC-TRAF - FINAL (SIGN/PAVEMENT MARKING) 05/01/2026 APPROVED - AS NOTED LFITZGERALD
Note: WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR tom to larry spoke with Cooper regarding street signage indicating where certain building numbers are so emergency knows where to go
U-ROW FINAL 05/01/2026 Disapproved - NO FEE LFITZGERALD
Note: WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR TOM TO LARRY no thermo for stripping at main entrance/need to relocate light pole and hand hole
UC-FINAL SITE INSPECTION 05/01/2026 PARTIALLY APPROVED LFITZGERALD
Note: WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR-Tom to Larry So drainage has some defincenties/parking stalls to be adjusted/need street signs indicating where certain buildingnumbers are located
UROW- CURBING & GUTTER 05/01/2026 APPROVED LFITZGERALD
Note: WAITING TO DISCUSS WALK WITH SENIOR INSPECTOR
UROW - FINAL DRAINAGE 05/01/2026 Disapproved -FEE REQUIRED JMYERS
Note: 5/4/26 MULTIPLE MES NOT INSTALLED, UNABLE TO VERIFY IF 60" PIPE UNDER ROAD IS CLEAN OF SEDIMENT, BANKS ADJACENT TO 60" PIPE ARE NOT STABILIZED ACCORDING WITH PLAN OR SWPPP.
UROW-RETENT/DETENT STABILI 05/01/2026 Disapproved -FEE REQUIRED JMYERS
Note: 5/4/26 BANKS ADJACENT TO 60" PIPE ARE NOT STABILIZED ACCORDING WITH PLAN OR SWPPP.
IRRIGATION AFFIDAVIT
LDSC-IRRIGATION FINAL
Note: 5/28/2026 4:18:01 PM- PREVIOUS INSPECTION NOTES Irrigation Affidavit is not approved because: 1. Incorrect Form - Use COPC Form 2. Notary is NOT rewquired and does not add credibilty 3. Requires signature and seal from Florida RLA or Certified Irrigation Professional
LDSC- LANDSCAPE / IRRIGATION AS-BUILT
LDSC- LANDSCAPE FINAL

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
ADMINISTRATIVE- SITE DEVELOP ¤125.00 04/30/2026
INSPECTION - GENERAL ¤360.00 04/30/2026
SITE DEVELOPMENT ADMIN PLANNIN ¤179.00 04/30/2026
SITE INSPECTION ¤513.00 04/30/2026
SITE PLAN 29 ¤29.00 04/30/2026
REINSPECTION- SITE INSPECTOR ¤40.00
REINSPECTION- SITE INSPECTOR ¤40.00
Fees Total Due: ¤80.00 Total Paid: ¤1,206.00