I want to search for...

Permit #2026050421

Permit Details

Status: INSPECT

Parcel Id: 21-12-31-5560-00000-0900
CONDITIONED SPACE: 1501 sqft
GARAGE: 403 sqft
OPENED PORCH (WITH ROOF) : 119 sqft
Total Square Footage: 2023 sqft
Subdivision: 2336 - SEMINOLE PALMS SUBDIVISION PHASE 1
Job Phone: 407-717-5418
Location Address: 135 SAGO CT
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
Issue Date: 05/29/2026
NOC: RECORDED
Applicant name: CARLOS ANTONIO SERRANO
Owner: NVR INC

Address

1409 TECH BLVD

TAMPA, FL 33619

Address

SUITE 202

TAMPA, FL 33619

Lot: 90
Contracted Stated Job Value: ¤150,344.00
Job Description: SINGLE FAMILY RESIDENCE
Type: CN

Contractor

RYAN HOMES
Status Location Address Mailing Address State License Number Phone
ACTIVE

8649 BAYPINE RD

JACKSONVILLE, FL 32256

BLDG 7, STE 202

JACKSONVILLE, FL 32256

CBC1256450 (Exp: 08/31/2026) 407-717-5418

Sub Contractors

JOSEPH H STRADA JR
Status Location Address State License Number Phone
ACTIVE

3400 ST JOHNS PKWY

SANFORD, FL 32771

CAC043953 (Exp: 08/31/2026) 877-906-1113
JOSEPH H STRADA JR
Status Location Address State License Number Phone
ACTIVE

3400 ST JOHNS PKWY

SANFORD, FL 32771

CAC043953 (Exp: 08/31/2026) 877-906-1113
BRITT MICHAEL JENKINS
Status Location Address State License Number Phone
ACTIVE

86 COLUMBIA DR

POOLER, GA 31322

CFC1430770 (Exp: 08/31/2026) 912-330-8151
JACK DOUGLAS LANIER
Status Location Address State License Number Phone Fax
ACTIVE

485 COMMERCE WAY

LONGWOOD , FL 32750

CCC058022 (Exp: 08/31/2026) (321)441-2300 (321)441-2313

Inspection History

Type Request Date Result Inspector
MONOLITHIC SLAB 06/03/2026 APPROVED KSANDOE
PLUMBING 1ST ROUGH UNDERGROUND 06/02/2026 APPROVED RSIMS
Note: 5/29/26: Main underground water service piping is installed from house to meter location and a pressure test with gauge has been applied. Only the Meter connection will need to be checked prior to Final Inspection. RS
WATER METER INSTALLATION REQUEST 06/02/2026 APPROVED ISANDERSON
FORMBOARD SURVEY (OFFICE USE ONLY) 06/01/2026 APPROVED PFLANAGAN
GRAVITY SEWER TEST 05/29/2026 APPROVED RSIMS
SEWER TIE IN 05/29/2026 APPROVED RSIMS
ELECTRIC - EARLY POWER
PEP TANK INSTALLATION REQUEST
U-CROSS CONNECTION
ROW- PRE-APRON (PRE-POUR)
ROW - FINAL APRON (AFTER POUR)
ROW - FINAL INSPECTION
U -UTILITY RESIDENTIAL FINAL
LATH/BRICK/ WATER BARRIER
ALL ROUGH
Note: 5/29/26: Main underground water service piping is installed from house to meter location and a pressure test with gauge has been applied. Only the Meter connection will need to be checked prior to Final Inspection. RS
WALL SHEATHING
ROOF SHEATHING / BRACES/TIES/DOWN CELL
ROOF VALLEY & METAL
INSULATION
DRYWALL NAILING
BLD - BUILDING FINAL

Review History

Department Status Date In Date Out
SW1 COMPLETE 05/29/2026 06/01/2026
Note: Released By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM
ZON COMPLETE 05/29/2026 05/29/2026
Note: Released By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM
ZON COMPLETE 05/28/2026 05/28/2026
Note: Released By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM
MECH COMPLETE 05/19/2026 05/19/2026
Note: Released By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM
ZON HOLD 05/19/2026 05/19/2026
Note: Held By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM 2nd request Landscape plan is missing the left street side plantings required
URB COMPLETE 05/19/2026 05/21/2026
Note: Released By: JOHN BEAUDET - (386)986-2456 - JBEAUDET@PALMCOASTGOV.COM
SW1 COMPLETE 05/19/2026 05/27/2026
Note: Released By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM
ENGIN1 COMPLETE 05/19/2026 05/20/2026
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
ZON HOLD 05/12/2026 05/12/2026
Note: Held By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM Landscape plan is missing the left street side plantings required Site plan must show/label the left side UD Easement on the street side
BLD COMPLETE 05/11/2026 05/14/2026
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
CUSVC COMPLETE 05/11/2026 05/14/2026
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ELEC COMPLETE 05/11/2026 05/14/2026
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 05/11/2026 05/12/2026
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
GAS CANCEL 05/11/2026 05/12/2026
LOCATE COMPLETE 05/11/2026 05/12/2026
Note: Released By: IVAN SANDERSON - -
MECH HOLD 05/11/2026 05/12/2026
Note: Held By: CHRIS PISCITELLI - (386)986-2574 - CPISCITELLI@PALMCOASTGOV.COM Direction house faces on Energy Calcs does not match the site plan. Revise to match per R405.4.2.1 FBC Energy Conservation 2023 8Th Edition
SW1 HOLD 05/11/2026 05/19/2026
Note: Held By: RODNEY RICKS - (386)986-4726 - RRICKS@PALMCOASTGOV.COM - Provide the proposed FFEs for both adjacent lots.
ZON HOLD 05/11/2026 05/12/2026
Note: Held By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM Landscape plan is missing the left street side plantings required
URB HOLD 05/11/2026 05/13/2026
Note: Held By: JOHN BEAUDET - (386)986-2456 - JBEAUDET@PALMCOASTGOV.COM Need to add 2 additional shrubs to the left side facing the ROW. 6 total req..

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
WATER-METER ¤874.47 05/29/2026
WATER- TURN ON ¤50.00 05/29/2026
ADMINISTRATIVE RESIDENTIAL ¤30.00 05/29/2026
INSPECTION - RESIDENTIAL ¤805.75 05/29/2026
PLAN REVIEW - RESIDENTIAL ¤228.54 05/29/2026
FC IMPACT FEE EMS ¤62.00 05/29/2026
FC IMPACT FEE LAW ENFORCEMENT ¤218.00 05/29/2026
FC IMPACT FEE LIBRARY ¤268.00 05/29/2026
FIRE RES IMPACT FEE 10-25 ¤942.00 05/29/2026
WATER METER W/OUT TAP ¤965.03 05/29/2026
PARKS IMPACT FEE 10-25 ¤3,164.00 05/29/2026
RECLAIM WATER PERMIT INSPECTIO ¤40.00 05/29/2026
RSI DRIVEWAY AFTER POUR ¤16.25 05/29/2026
RSE DRIVE PRE POUR INSPECTION ¤32.50 05/29/2026
RSI FORMBOARD REVIEW ¤16.25 05/29/2026
RSI PLAN REVIEW NEW ¤48.75 05/29/2026
RSI FNL SURVEY/GRADING CERT ¤48.75 05/29/2026
RSI ROW FINAL INSPECTION ¤16.25 05/29/2026
SURCHARGE FS 533.721 ¤10.64 05/29/2026
SURCHARGE - FS 468.631 ¤15.96 05/29/2026
TRANSP RES IMPACT FEE 10-25 ¤5,658.77 05/29/2026
TRANSP RES IMPACT FEE 10-25 (¤5,658.77) 05/29/2026
WASTEWATER PERM INSPECTION ¤80.00 05/29/2026
WASTEWATER PERM REVIEW ¤25.00 05/29/2026
SEWER CAPITAL FACILITY ¤2,368.69 05/29/2026
WATER CAPITAL FACILITY FEE ¤2,037.94 05/29/2026
WATER PERMIT REVIEW ¤25.00 05/29/2026
SITE PLAN 30 ¤30.00 05/29/2026
Fees Total Due: ¤0.00 Total Paid: ¤12,419.77