Permit #2026051098

Permit Details

Status: APPLY

Parcel Id: 07-11-31-7010-00040-0010
CONDITIONED SPACE: 2067 sqft
GARAGE: 397 sqft
OPENED PORCH (WITH ROOF) : 157 sqft
Total Square Footage: 2621 sqft
Block: 00040
Subdivision: 2137 - SECTION 10-FLORIDA PARK
Job Phone: 407-476-8195
Location Address: 37 FERBER LN
Type: BR - BUILDING RESIDENTIAL -SINGLE FAMILY
NOC: NO DOCUMENTATION
Applicant name: CARLETTE RENE WITTE
Owner: INB BFS LAND LLC

Address

7380 WEST SAND LAKE ROAD

ORLANDO, FL 32819

Address

SUITE 600

ORLANDO, FL 32819

Lot: 0010
Contracted Stated Job Value: ¤275,000.00
Job Description: Single Family Residence
Type: CN

Contractor

INNOVATIVE NATIONWIDE BUILDERS INC
Status Location Address State License Number Phone
ACTIVE

3670 MAGUIRE BLVD #220

,

CRC1330026 (Exp: 08/31/2026) 855-694-6634

Sub Contractors

JASON LEE JAMES
Status Location Address State License Number Phone
ACTIVE

217 N WESTMONTE DR SUITE 1007

ALTAMONTE SPRINGS, FL 32714

CAC1820196 (Exp: 08/31/2026) 407-404-4000
ANTHONY OKEITH FENNELL
Status Location Address State License Number Phone
ACTIVE

217 N. WESTMONTE DR, SUITE 1007

ALTAMONTE SPRINGS, FL 32714

EC13011194 (Exp: 08/31/2026) 407-404-4000
HEATH EDWARD SANFORD
Status Location Address State License Number Phone
ACTIVE

126 EAST END RD

SAN MATEO, FL 32187

CFC1429896 (Exp: 08/31/2026) 386-871-8823
TERRY BRICE DICKERSON
Status Location Address State License Number Phone
ACTIVE

4300 ST JOHN'S PARKWAY

ALPHARETTA, GA 30009

CCC1326209 (Exp: 08/31/2026) 407-548-6733

Inspection History

Type Request Date Result Inspector
FORMBOARD SURVEY (OFFICE USE ONLY)
GEOTECHNICAL REPORT APPROVAL (OFFICE USE)
PLUMBING 1ST ROUGH UNDERGROUND
GRAVITY SEWER TEST
SEWER TIE IN
ELECTRIC - EARLY POWER
MONOLITHIC SLAB
LATH/BRICK/ WATER BARRIER
TIE BEAM / LINTEL
ALL ROUGH
WALL SHEATHING
ROOF SHEATHING / BRACES/TIES/DOWN CELL
ROOF VALLEY & METAL
INSULATION
DRYWALL NAILING
BLD - BUILDING FINAL
WILDLIFE CHECK - ENVIRONMENTAL
WATER METER INSTALLATION REQUEST
PEP TANK INSTALLATION REQUEST
U-CROSS CONNECTION
ROW- PRE-APRON (PRE-POUR)
ROW - FINAL APRON (AFTER POUR)
ROW- FINAL SURVEY/GRADING CERTIFICATION
ROW - FINAL INSPECTION
U -UTILITY RESIDENTIAL FINAL

Review History

Department Status Date In Date Out
SWALE COMPLETE 05/29/2026 06/04/2026
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
PLENV HOLD 05/28/2026 06/01/2026
Note: Held By: DYLAN RODRIGUEZ - (386)986-2320 - DRODRIGUEZ@PALMCOASTGOV.COM Staff conduced a site visit on 06/01/26 and found potentially occupied Gopher Tortoise burrow. Please either provide a Gopher Tortoise survey by a QEP that shows the burrow is not within 25ft of construction activities or an approved After Action Report from FWC after relocation activities have been completed.
BLD COMPLETE 05/27/2026 06/01/2026
Note: Released By: PETER KNAPIK - (386)986-3783 - PKNAPIK@PALMCOASTGOV.COM
CUSVC COMPLETE 05/27/2026 06/01/2026
Note: Released By: HALEIGH HAND - - HHAND@PALMCOASTGOV.COM
ELEC COMPLETE 05/27/2026 06/01/2026
Note: Released By: JOSH MUNSON - (386)986-4736 - JMUNSON@PALMCOASTGOV.COM
ENGIN1 COMPLETE 05/27/2026 05/29/2026
Note: Released By: LEVI SALYERDS - (386)986-2575 - LSALYERDS@PALMCOASTGOV.COM
GAS CANCEL 05/27/2026 06/02/2026
LOCATE COMPLETE 05/27/2026 05/28/2026
Note: Released By: IVAN SANDERSON - -
MECH COMPLETE 05/27/2026 06/02/2026
Note: Released By: KENNETH SANDOE - - KSANDOE@PALMCOASTGOV.COM
SW1 HOLD 05/27/2026 06/03/2026
Note: Held By: PARREN FLANAGAN - (386)986-2392 - PFLANAGAN@PALMCOASTGOV.COM The proposed FFE of this project is .85 higher the adjacent lot to the left. FFE can not be greater then 10" above the adjacent lot.
ZON COMPLETE 05/27/2026 05/28/2026
Note: Released By: LIBBY RAYBURN - - LRAYBURN@PALMCOASTGOV.COM
PLENV PENDING
SW1 PENDING

Fees & Payments

(Permit is not ready for pickup until the permit has been processed and fees appear)
Description Amount Due Date Paid
WATER- TURN ON ¤50.00
WASTEWATER MAIN EXTENSION IMPA ¤2,385.00
WATER METER W/ TAP ¤2,326.93
SEWER CAPITAL FACILITY ¤4,415.00
WATER CAPITAL FACILITY FEE ¤4,084.25
WATER MAIN EXTENSION IMPACT ¤980.13
Fees Total Due: ¤14,241.31 Total Paid: ¤0.00