Permit #2020100356

Permit Details
TypeBR - BUILDING RESIDENTIAL -SINGLE FAMILY
StatusCOED
Date Issued10/12/2020
Expiration Date11/18/2021
Job Value¤271,000.00
Contractor Est. Cost¤218,088.00
Address16 LARAMIE DR
Parcel Number07-11-31-7037-00180-0090
Subdivision2176 - SECTION 37-LAKEVIEW
Block00180
Lot0090
ApplicantBRIAN ANDREW GAZZOLI (CN) — (386) 246-6123
OwnerSEAGATE HOMES LLC, 185 CYPRESS POINT PKWY, STE 7 , PALM COAST FL 32164
Notice of CommencementRECORDED
Early PowerNO
Job DescriptionSINGLE FAMILY RESIDENCE
Square Footage
LocationArea (sq ft)
CONDITIONED SPACE2,208
GARAGE438
OPENED PORCH (WITH ROOF) 162
OPENED PORCH (WITH ROOF) 35
Contractor
NameBRIAN ANDREW GAZZOLI
DBASEAGATE HOMES, LLC
ClassGENERAL CONTRACTOR CERTIFIED
Phone386-246-6132
EmailZHARRIS@SEAGATEHOMES.COM;BSMITH@SEAGATEHOMES.COM;DFRANKLIN@SEAGATEHOMES.COM;CPAYNE@SEAGATEHOMES.COM;BLAINE.GAZZOLI@SEAGATEHOMES.COM
State LicenseCGC1518372
State Exp. 08/31/2028
Liability Exp. 06/30/2027
Workers Comp Exp. 01/01/2027
LBTR #
LBTR Exp.
Status ACTIVE
Subcontractors
NameDBAClassLicenseLic. Exp.Status
RICHARD H SIMMONS JR SIMMONS ELECTRIC, INC ELECTRIC RESIDENTIAL SPECIALTY CERTIFIED ES12001217 08/31/2028 ACTIVE
MICHAEL FRANK MORELLO MIKE MORELLO INC MECHANICAL CONTRACTOR CERTIFIED CAC1819466 08/31/2028 ACTIVE
DENNIS GENE GAINEY ADVANCED PLUMBING INC. PLUMBING CONTRACTOR CERTIFIED CFC046004 08/31/2026 INACTIVE
ANDREW SCOTT DIGAETANO JR AK CERTIFIED CONTRACTING LLC ROOFING CONTRACTOR CERTIFIED CCC1331606 08/31/2028 ACTIVE
Inspection History
TypeRequest DateInspectorResultNotes
U -UTILITY RESIDENTIAL FINAL 05/17/2021 DHANEY FINAL APPROVED
BLD - BUILDING FINAL 05/17/2021 FWILLIS FINAL APPROVED
U-CROSS CONNECTION 05/17/2021 DHANEY APPROVED
ROW - STORMWATER FINAL 05/14/2021 KRUTH APPROVED
ROW - FINAL APRON (AFTER POUR) 05/14/2021 KRUTH APPROVED
ROW FIELD SURVEY /GRADING CERTIFICATION 05/14/2021 KRUTH APPROVED
FINAL SURVEY (OFFICE USE ONLY) 05/14/2021 KRUTH APPROVED
ROW- PRE-APRON (PRE-POUR) 04/15/2021 KRUTH APPROVED
ELECTRIC - EARLY POWER 04/08/2021 JMUNSON APPROVED - AS NOTED
ELECTRIC - EARLY POWER 04/06/2021 JMUNSON Disapproved - NO FEE
GRAVITY SEWER TEST 03/15/2021 JBODEN APPROVED
U - SEWER TIE IN 03/15/2021 JBODEN APPROVED
PEP TANK INSTALLATION REQUEST 02/24/2021 CSTONE APPROVED
INSULATION 02/19/2021 FWILLIS APPROVED
LATH/BRICK/ WATER BARRIER 02/18/2021 FWILLIS APPROVED
ALL ROUGH 02/16/2021 FWILLIS APPROVED
ROOF VALLEY & METAL 02/11/2021 FWILLIS APPROVED
ROOF SHEATHING / BRACES/TIES/DOWN CELL 02/03/2021 FWILLIS APPROVED
TIE BEAM / LINTEL 01/13/2021 FWILLIS APPROVED
FOUND SURVEY APPROVED (OFFICE) 01/08/2021 TBAKER APPROVED
MONOLITHIC SLAB 12/21/2020 FWILLIS APPROVED
PLUMBING 1ST ROUGH UNDERGROUND 11/25/2020 FWILLIS APPROVED
ROW - DRAINAGE 11/19/2020 RGROSS APPROVED
ROW - DRAINAGE 11/16/2020 RGROSS PARTIALLY APPROVED
WATER METER INSTALLATION REQUEST 10/22/2020 CSTONE APPROVED
Review History
DepartmentDate InDate OutStatusNotes
BLD 02/03/2021 02/10/2021 COMPLETE
ENGIN1 01/07/2021 01/08/2021 COMPLETE
ZON 01/07/2021 01/07/2021 COMPLETE
SW1 11/10/2020 11/10/2020 COMPLETE
ENGIN1 10/21/2020 10/22/2020 COMPLETE
SW1 10/21/2020 10/27/2020 HOLD
ZON 10/21/2020 10/21/2020 COMPLETE
SWALE 10/08/2020 12/01/2020 COMPLETE
ZON 10/07/2020 10/08/2020 COMPLETE
SW1 10/07/2020 10/08/2020 COMPLETE
PLUM 10/07/2020 10/10/2020 COMPLETE
MECH 10/07/2020 10/08/2020 COMPLETE
LOCATE 10/07/2020 10/09/2020 COMPLETE
ENGIN1 10/07/2020 10/08/2020 COMPLETE
ELEC 10/07/2020 10/08/2020 COMPLETE
CUSVC 10/07/2020 10/09/2020 COMPLETE
BLD 10/07/2020 10/10/2020 COMPLETE
Payment History
DescriptionDate PaidAmount DueAmount Paid
REVISION 05/07/2021 ¤40.00 ¤40.00
SITE PLAN 20 10/12/2020 ¤20.00 ¤20.00
SURCHARGE FS 533.721 10/12/2020 ¤2.00 ¤2.00
SURCHARGE - FS 468.631 10/12/2020 ¤2.00 ¤2.00
STORM WATER PERMIT FEES 10/12/2020 ¤80.00 ¤80.00
3% TRANS IMPACT FEE CREDIT 10/12/2020 (¤50.22) (¤50.22)
SEWER CREDIT 10/12/2020 (¤850.00) (¤850.00)
SEWER INSPECTION 10/12/2020 ¤25.00 ¤25.00
SEWER CAPITAL FACILITY 10/12/2020 ¤4,596.07 ¤4,596.07
WATER CAPITAL FACILITY FEE 10/12/2020 ¤3,374.18 ¤3,374.18
METER - DEPOSIT 10/12/2020 ¤60.00 ¤60.00
WATER- TURN ON 10/12/2020 ¤25.00 ¤25.00
ADMIN FEE 10/12/2020 ¤20.00 ¤20.00
CONNECTION FEES 10/12/2020 ¤1,002.88 ¤1,002.88
BUILDING DISCOUNT 100% 10/12/2020 (¤1,338.20) (¤1,338.20)
ELECTRIC FEE 10/12/2020 ¤222.60 ¤222.60
3% FIRE IMPACT FEE CREDIT 10/12/2020 (¤6.70) (¤6.70)
IMPACT FEE FIRE 10/12/2020 ¤223.38 ¤223.38
IMPACT FEE PARKS 10/12/2020 ¤849.24 ¤849.24
IMPACT FEE SCHOOL 10/12/2020 ¤3,600.00 ¤3,600.00
IMPACT FEE TRANSPORTATION 10/12/2020 ¤1,674.00 ¤1,674.00
MECHANICAL FEE 10/12/2020 ¤222.60 ¤222.60
WATER -IRRIGATION INSPECTION 10/12/2020 ¤25.00 ¤25.00
3% PARKS IMPACT FEE CREDIT 10/12/2020 (¤25.48) (¤25.48)
PLAN CHECK FEE 10/12/2020 ¤108.40 ¤108.40
PLUMBING FEE 10/12/2020 ¤222.60 ¤222.60
NEW RESIDENTIAL INSPECTIONS 10/12/2020 ¤542.00 ¤542.00