Permit #2026100164
Permit Details
TypeCIA - COMMERCIAL INTERIOR EXTERIOR ALTERATION
StatusISSUED
Date Issued10/27/2026
Expiration Date04/30/2027
Job Value¤540,000.00
Contractor Est. Cost¤540,000.00
Address5838 STATE HWY 100 E
Parcel Number08-12-31-4946-00000-00B0
Subdivision -
Block000B0
Lot0110
ApplicantERIC GLENN DRUMMOND (CN) — 352-318-1259
OwnerTRIPLE M GEORGIA INVESTMENTS LLC, 346 N 11TH STREET , FLAGLER BEACH FL 32136
Notice of CommencementRECORDED
Early PowerNO
Job DescriptionUNIT 1 - HUEY MAGOOS - INTERIOR BUILDOUT
Contractor
NameERIC GLENN DRUMMOND
DBADRUMMOND CONSTRUCTION GROUP LLC
ClassGENERAL CONTRACTOR CERTIFIED
Phone352-318-1259
EmailERIC@DRUMMONDCONSTRUCTIONGROUP.COM
State LicenseCGC1521849
State Exp.
08/31/2028
Liability Exp.
06/23/2027
Workers Comp Exp.
LBTR #
LBTR Exp.
Status
ACTIVE
Subcontractors
| Name | DBA | Class | License | Lic. Exp. | Status |
|---|---|---|---|---|---|
| GLEN WILLIAM KEHLE | KEHLE PLUMBING INC. | PLUMBING CONTRACTOR CERTIFIED | CFC057241 | 08/31/2028 | ACTIVE |
| GLEN WILLIAM KEHLE | KEHLE PLUMBING INC. | PLUMBING CONTRACTOR CERTIFIED | CFC057241 | 08/31/2028 | ACTIVE |
| AUSTIN KYLE WRIGHT | WRIGHT BROTHERS HEATING AND AIR CONDITIONING, LLC | MECHANICAL CONTRACTOR CERTIFIED | CAC1824035 | 08/31/2028 | ACTIVE |
| PAUL NOEL BIELEFELDT | PAULS ELECTRICAL CONTRACTING, INC | ELECTRICAL CONTRACTOR CERTIFIED | EC0001646 | 08/31/2028 | ACTIVE |
Inspection History
| Type | Request Date | Inspector | Result | Notes |
|---|---|---|---|---|
| BLD - GREASE INTERCEPTOR PLUMBING & VENTING | Pending | |||
| PLUMBING 1ST ROUGH | Pending | |||
| PLUMBING 2ND ROUGH | Pending | |||
| PLUMBING FINAL | Pending | |||
| HVAC ROUGH | Pending | |||
| HVAC FINAL | Pending | |||
| ELECTRIC 2ND ROUGH | Pending | |||
| ELECTRIC FINAL | Pending | |||
| GAS ROUGH | Pending | |||
| GAS FINAL | Pending | |||
| MONOLITHIC SLAB | Pending | |||
| FRAMING | Pending | |||
| FIREWALL FRAMING | Pending | |||
| FIREWALL FINAL | Pending | |||
| FIREWALL PENETRATIONS | Pending | |||
| FIREWALL DRYWALL NAILING | Pending | |||
| ABOVE CEILING | Pending | |||
| INSULATION | Pending | |||
| DRYWALL NAILING | Pending | |||
| BUILDING FINAL | Pending | |||
| FIRE FINAL | Pending | |||
| U-GREASE INTERCEPTOR FLOW/DYE TESTED | Pending | |||
| U-WATER METER INSTALLATION/VERIFICATION | Pending | |||
| U - UTILITY COMMERCIAL FINAL | Pending |
Review History
| Department | Date In | Date Out | Status | Notes |
|---|---|---|---|---|
| MECH | 10/26/2026 | 10/27/2026 | COMPLETE | |
| BLD | 10/26/2026 | 10/27/2026 | COMPLETE | |
| FI1 | 10/26/2026 | 10/27/2026 | COMPLETE | |
| BLD | 10/06/2026 | 10/15/2026 | HOLD | |
| DSD | 10/06/2026 | 10/06/2026 | COMPLETE | |
| ELEC | 10/06/2026 | 10/19/2026 | COMPLETE | |
| FI1 | 10/06/2026 | 10/19/2026 | HOLD | |
| MECH | 10/06/2026 | 10/14/2026 | HOLD | |
| PLUM | 10/06/2026 | 10/14/2026 | COMPLETE | |
| UD1 | 10/06/2026 | 10/16/2026 | COMPLETE | |
| UD2 | 10/06/2026 | 10/07/2026 | COMPLETE | |
| GAS | 10/06/2026 | 10/14/2026 | COMPLETE |
Payment History
| Description | Date Paid | Amount Due | Amount Paid |
|---|---|---|---|
| ADMINISTRATIVE - COMMERCIAL | 10/27/2026 | ¤75.00 | ¤75.00 |
| INSPECTION COMMERCIAL | 10/27/2026 | ¤3,780.00 | ¤3,780.00 |
| INSPECTION - FIRE COMMERCIAL | 10/27/2026 | ¤135.00 | ¤135.00 |
| PLAN REVIEW - COMMERCIAL | 10/27/2026 | ¤621.00 | ¤621.00 |
| SURCHARGE FS 533.721 | 10/27/2026 | ¤46.11 | ¤46.11 |
| SURCHARGE - FS 468.631 | 10/27/2026 | ¤69.17 | ¤69.17 |
| SITE PLAN 30 | 10/27/2026 | ¤30.00 | ¤30.00 |