Permit #2026100875
Permit Details
TypeBR - BUILDING RESIDENTIAL -SINGLE FAMILY
StatusISSUED
Date Issued11/17/2026
Expiration Date11/17/2027
Job Value¤389,000.00
Contractor Est. Cost¤203,000.00
Address253 HAWTHORN AVE
Parcel Number05-12-31-2755-00000-0270
Subdivision2313 - THE GABLES SUBDIVISION AT TOWN CENTER
Block
Lot27
ApplicantRAYMOND CLIVE CROSBY (CN) — 904-219-3385
OwnerDR HORTON INC - JACKSONVILLE, 4220 RACE TRACK ROAD SUITE 100, SAINT JOHNS FL 32259
Notice of CommencementRECORDED
Early PowerNO
Job DescriptionSINGLE FAMILY
Square Footage
| Location | Area (sq ft) |
|---|---|
| CONDITIONED SPACE | 2,030 |
| GARAGE | 417 |
| OPENED PORCH (WITH ROOF) | 179 |
Contractor
NameRAYMOND CLIVE CROSBY
DBADR HORTON, INC.
ClassBUILDING CONTRACTOR CERTIFIED
Phone904-268-2845
EmailJMMEADE@DRHORTON.COM;RCCROSBY@DRHORTON.COM;CWHARRELL@DRHORTON.COM;WJFAUST@DRHORTON.COM;ABBAKER@DRHORTON.COM;CTALBERT@DRHORTON.COM;JAMOORE@DRHORTON.COM;JCWARREN@DRHORTON.COM;GMMONTOYA@DRHORTON.COM;SMLAKE@DRHORTON.COM;BMOORE2@DRHORTON.COM;CGSIMON@DRHORTON.COM;CBARRERA@DRHORTON.COM;DMMACKEY@DRHORTON.COM;JASEWELL@DRHORTON.COM
State LicenseCBC058997
State Exp.
08/31/2028
Liability Exp.
07/01/2027
Workers Comp Exp.
07/01/2027
LBTR #2007000699
LBTR Exp.09/30/2007
Status
ACTIVE
Subcontractors
| Name | DBA | Class | License | Lic. Exp. | Status |
|---|---|---|---|---|---|
| COREY MICHAEL TENNANT | A/C DESIGNS OF ST AUGUSTINE, LLC | AIR CONDITIONING, CLASS B - CERTIFIED | CAC1819063 | 08/31/2028 | ACTIVE |
| PAUL ERIC FORSTER | PRESTO PLUMBING LLC | PLUMBING CONTRACTOR CERTIFIED | CFC1429261 | 08/31/2028 | ACTIVE |
| JAMES M GREENSLADE | GREENSLADE ELECTRIC, LLC | ELECTRICAL CONTRACTOR CERTIFIED | EC13006083 | 08/31/2028 | ACTIVE |
| BOBBY WAYNE CAMPBELL | BCR, INC | ROOFING CONTRACTOR CERTIFIED | CCC1326752 | 08/31/2028 | ACTIVE |
Inspection History
| Type | Request Date | Inspector | Result | Notes |
|---|---|---|---|---|
| FORMBOARD SURVEY (OFFICE USE ONLY) | Pending | |||
| PLUMBING 1ST ROUGH UNDERGROUND | Pending | |||
| GRAVITY SEWER TEST | Pending | |||
| SEWER TIE IN | Pending | |||
| ELECTRIC - EARLY POWER | Pending | |||
| MONOLITHIC SLAB | Pending | |||
| LATH/BRICK/ WATER BARRIER | Pending | |||
| ALL ROUGH | Pending | |||
| WALL SHEATHING | Pending | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | Pending | |||
| ROOF VALLEY & METAL | Pending | |||
| INSULATION | Pending | |||
| DRYWALL NAILING | Pending | |||
| BLD - BUILDING FINAL | Pending | |||
| WATER METER INSTALLATION REQUEST | Pending | |||
| U-CROSS CONNECTION | Pending | |||
| ROW- PRE-APRON (PRE-POUR) | Pending | |||
| ROW - FINAL APRON (AFTER POUR) | Pending | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | Pending | |||
| ROW - FINAL INSPECTION | Pending | |||
| U -UTILITY RESIDENTIAL FINAL | Pending |
Review History
| Department | Date In | Date Out | Status | Notes |
|---|---|---|---|---|
| ZON | 11/03/2026 | 11/03/2026 | COMPLETE | |
| ENGIN1 | 11/03/2026 | 11/04/2026 | COMPLETE | |
| BLD | 10/27/2026 | 10/30/2026 | COMPLETE | |
| CUSVC | 10/27/2026 | 11/02/2026 | COMPLETE | |
| ELEC | 10/27/2026 | 11/02/2026 | COMPLETE | |
| ENGIN1 | 10/27/2026 | 10/28/2026 | COMPLETE | |
| GAS | 10/27/2026 | 10/29/2026 | CANCEL | |
| LOCATE | 10/27/2026 | 10/30/2026 | COMPLETE | |
| MECH | 10/27/2026 | 10/29/2026 | COMPLETE | |
| SW1 | 10/27/2026 | 11/02/2026 | COMPLETE | |
| ZON | 10/27/2026 | 10/28/2026 | HOLD | |
| URB | 10/27/2026 | 11/03/2026 | COMPLETE |
Payment History
| Description | Date Paid | Amount Due | Amount Paid |
|---|---|---|---|
| WATER-METER | 11/17/2026 | ¤874.47 | ¤874.47 |
| WATER- TURN ON | 11/17/2026 | ¤50.00 | ¤50.00 |
| ADMINISTRATIVE RESIDENTIAL | 11/17/2026 | ¤30.00 | ¤30.00 |
| INSPECTION - RESIDENTIAL | 11/17/2026 | ¤1,069.75 | ¤1,069.75 |
| PLAN REVIEW - RESIDENTIAL | 11/17/2026 | ¤303.42 | ¤303.42 |
| FC IMPACT FEE EMS | 11/17/2026 | ¤62.00 | ¤62.00 |
| FC IMPACT FEE LAW ENFORCEMENT | 11/17/2026 | ¤218.00 | ¤218.00 |
| FC IMPACT FEE LIBRARY | 11/17/2026 | ¤268.00 | ¤268.00 |
| FIRE RES IMPACT FEE 10-25 | 11/17/2026 | ¤942.00 | ¤942.00 |
| WATER METER W/OUT TAP | 11/17/2026 | ¤965.03 | ¤965.03 |
| PARKS IMPACT FEE 10-25 | 11/17/2026 | ¤3,164.00 | ¤3,164.00 |
| RECLAIM WATER PERMIT INSPECTIO | 11/17/2026 | ¤40.00 | ¤40.00 |
| RSI DRIVEWAY AFTER POUR | 11/17/2026 | ¤16.25 | ¤16.25 |
| RSE DRIVE PRE POUR INSPECTION | 11/17/2026 | ¤32.50 | ¤32.50 |
| RSI FORMBOARD REVIEW | 11/17/2026 | ¤16.25 | ¤16.25 |
| RSI PLAN REVIEW NEW | 11/17/2026 | ¤48.75 | ¤48.75 |
| RSI FNL SURVEY/GRADING CERT | 11/17/2026 | ¤48.75 | ¤48.75 |
| RSI ROW FINAL INSPECTION | 11/17/2026 | ¤16.25 | ¤16.25 |
| SCHOOL BOARD IMPACT FEE RES | 11/17/2026 | ¤5,450.00 | ¤5,450.00 |
| SURCHARGE FS 533.721 | 11/17/2026 | ¤14.03 | ¤14.03 |
| SURCHARGE - FS 468.631 | 11/17/2026 | ¤21.05 | ¤21.05 |
| TRANSP RES IMPACT FEE 10-25 | 11/17/2026 | ¤7,653.10 | ¤7,653.10 |
| WASTEWATER PERM INSPECTION | 11/17/2026 | ¤80.00 | ¤80.00 |
| WASTEWATER PERM REVIEW | 11/17/2026 | ¤25.00 | ¤25.00 |
| WATER PERMIT REVIEW | 11/17/2026 | ¤25.00 | ¤25.00 |
| SITE PLAN 30 | 11/17/2026 | ¤30.00 | ¤30.00 |