Permit #2026110056
Permit Details
TypeBR - BUILDING RESIDENTIAL -SINGLE FAMILY
StatusISSUED
Date Issued11/17/2026
Expiration Date11/17/2027
Job Value¤514,000.00
Contractor Est. Cost¤355,000.00
Address28 EVANSVILLE LN
Parcel Number07-11-31-7034-01020-0190
Subdivision2165 - SECTION 34-EASTHAMPTON
Block01020
Lot0190
ApplicantVLADIMIR VIZDOAGA (CN) — 305-450-2543
OwnerVR REALTY HOMES LLC, 19 EMMONS LANE , PALM COAST FL 32164
Notice of CommencementRECORDED
Early PowerNO
Job DescriptionSINGLE FAMILY RESIDENCE
Square Footage
| Location | Area (sq ft) |
|---|---|
| CONDITIONED SPACE | 2,500 |
| GARAGE | 744 |
| OPENED PORCH (WITH ROOF) | 440 |
| OPENED PORCH (WITH ROOF) | 62 |
Contractor
NameVLADIMIR VIZDOAGA
DBAVR REALTY HOMES LLC
ClassRESIDENTIAL CONTRACTOR REGISTERED
Phone305-450-2543
EmailVRREALTYHOMES@GMAIL.COM
State LicenseRR282812325
State Exp.
08/31/2027
Liability Exp.
08/16/2027
Workers Comp Exp.
LBTR #
LBTR Exp.
Status
ACTIVE
Subcontractors
| Name | DBA | Class | License | Lic. Exp. | Status |
|---|---|---|---|---|---|
| JUAN CARLOS GONZALEZ | GNLZ PLUMBING LLC | PLUMBING CONTRACTOR REGISTERED | RF11067806 | 08/31/2027 | ACTIVE |
| JOSEPH C WRIGHT | QUANTUM ELECTRICAL CONTRACTORS INC | ELECTRICAL CONTRACTOR CERTIFIED | EC13003278 | 08/31/2028 | ACTIVE |
| TIMUR ISPARYAN | AVALON HEATING AND AIR LLC | MECHANICAL CONTRACTOR CERTIFIED | CMC1249968 | 08/31/2028 | ACTIVE |
| ALEXANDER BENITEZ | A&G FLORIDA ROOFING LLC | ROOFING CONTRACTOR CERTIFIED | CCC1333643 | 08/31/2028 | ACTIVE |
Inspection History
| Type | Request Date | Inspector | Result | Notes |
|---|---|---|---|---|
| FORMBOARD SURVEY (OFFICE USE ONLY) | Pending | |||
| GEOTECHNICAL REPORT APPROVAL (OFFICE USE) | Pending | |||
| PLUMBING 1ST ROUGH UNDERGROUND | Pending | |||
| GRAVITY SEWER TEST | Pending | |||
| SEWER TIE IN | Pending | |||
| ELECTRIC - EARLY POWER | Pending | |||
| MONOLITHIC SLAB | Pending | |||
| LATH/BRICK/ WATER BARRIER | Pending | |||
| TIE BEAM / LINTEL | Pending | |||
| ALL ROUGH | Pending | |||
| WALL SHEATHING | Pending | |||
| ROOF SHEATHING / BRACES/TIES/DOWN CELL | Pending | |||
| ROOF VALLEY & METAL | Pending | |||
| INSULATION | Pending | |||
| DRYWALL NAILING | Pending | |||
| BLD - BUILDING FINAL | Pending | |||
| WATER METER INSTALLATION REQUEST | Pending | |||
| PEP TANK INSTALLATION REQUEST | Pending | |||
| U-CROSS CONNECTION | Pending | |||
| ROW- PRE-APRON (PRE-POUR) | Pending | |||
| ROW - FINAL APRON (AFTER POUR) | Pending | |||
| ROW- FINAL SURVEY/GRADING CERTIFICATION | Pending | |||
| ROW - FINAL INSPECTION | Pending | |||
| U -UTILITY RESIDENTIAL FINAL | Pending |
Review History
| Department | Date In | Date Out | Status | Notes |
|---|---|---|---|---|
| MECH | 11/09/2026 | 11/10/2026 | COMPLETE | |
| SWALE | 11/04/2026 | PENDING | ||
| BLD | 11/03/2026 | 11/06/2026 | COMPLETE | |
| CUSVC | 11/03/2026 | 11/05/2026 | COMPLETE | |
| ELEC | 11/03/2026 | 11/09/2026 | COMPLETE | |
| ENGIN1 | 11/03/2026 | 11/04/2026 | COMPLETE | |
| GAS | 11/03/2026 | 11/04/2026 | CANCEL | |
| LOCATE | 11/03/2026 | 11/03/2026 | COMPLETE | |
| MECH | 11/03/2026 | 11/04/2026 | HOLD | |
| SW1 | 11/03/2026 | 11/04/2026 | COMPLETE | |
| ZON | 11/03/2026 | 11/03/2026 | COMPLETE |
Payment History
| Description | Date Paid | Amount Due | Amount Paid |
|---|---|---|---|
| WATER- TURN ON | 11/17/2026 | ¤50.00 | ¤50.00 |
| ADMINISTRATIVE RESIDENTIAL | 11/17/2026 | ¤30.00 | ¤30.00 |
| INSPECTION - RESIDENTIAL | 11/17/2026 | ¤1,413.50 | ¤1,413.50 |
| PLAN REVIEW - RESIDENTIAL | 11/17/2026 | ¤400.92 | ¤400.92 |
| FC IMPACT FEE EMS | 11/17/2026 | ¤62.00 | ¤62.00 |
| FC IMPACT FEE LAW ENFORCEMENT | 11/17/2026 | ¤218.00 | ¤218.00 |
| FC IMPACT FEE LIBRARY | 11/17/2026 | ¤268.00 | ¤268.00 |
| FIRE RES IMPACT FEE 10-25 | 11/17/2026 | ¤942.00 | ¤942.00 |
| PEP TANK INSTALL | 11/17/2026 | ¤756.74 | ¤756.74 |
| PARKS IMPACT FEE 10-25 | 11/17/2026 | ¤3,164.00 | ¤3,164.00 |
| RSI DRIVEWAY AFTER POUR | 11/17/2026 | ¤16.25 | ¤16.25 |
| RSE DRIVE PRE POUR INSPECTION | 11/17/2026 | ¤32.50 | ¤32.50 |
| RSI FORMBOARD REVIEW | 11/17/2026 | ¤16.25 | ¤16.25 |
| RSI PLAN REVIEW NEW | 11/17/2026 | ¤48.75 | ¤48.75 |
| RSI FNL SURVEY/GRADING CERT | 11/17/2026 | ¤48.75 | ¤48.75 |
| RSI ROW FINAL INSPECTION | 11/17/2026 | ¤16.25 | ¤16.25 |
| SCHOOL BOARD IMPACT FEE RES | 11/17/2026 | ¤5,450.00 | ¤5,450.00 |
| WASTEWATER MAIN EXTENSION IMPA | 11/17/2026 | ¤2,385.00 | ¤2,385.00 |
| SURCHARGE FS 533.721 | 11/17/2026 | ¤18.44 | ¤18.44 |
| SURCHARGE - FS 468.631 | 11/17/2026 | ¤27.67 | ¤27.67 |
| SW ENG RES REVIEW 240 | 11/17/2026 | ¤240.00 | ¤240.00 |
| WATER METER W/ TAP | 11/17/2026 | ¤2,326.93 | ¤2,326.93 |
| TRANSP RES IMPACT FEE 10-25 | 11/17/2026 | ¤9,425.00 | ¤9,425.00 |
| SEWER CREDIT | 11/17/2026 | (¤850.00) | (¤850.00) |
| WASTEWATER PERM INSPECTION | 11/17/2026 | ¤80.00 | ¤80.00 |
| WASTEWATER PERM REVIEW | 11/17/2026 | ¤25.00 | ¤25.00 |
| SEWER CAPITAL FACILITY | 11/17/2026 | ¤4,415.00 | ¤4,415.00 |
| WATER CAPITAL FACILITY FEE | 11/17/2026 | ¤4,084.25 | ¤4,084.25 |
| WATER PERMIT REVIEW | 11/17/2026 | ¤25.00 | ¤25.00 |
| WATER MAIN EXTENSION IMPACT | 11/17/2026 | ¤980.13 | ¤980.13 |
| SITE PLAN 30 | 11/17/2026 | ¤30.00 | ¤30.00 |