Street Resurfacing
The goal of this project is to ensure a high-quality roadway system while using the City's maintenance funds wisely. In 2017, Transmap was hired to assess the City's road network. The selection of roadways for milling and resurfacing in this contract was based on the lowest pavement condition index (PCI) levels identified through the Transmap digital survey, as well as consideration of future roadway projects. The aim is to restore 32 lane miles of arterial roadways to excellent condition across the city. Please note that this project is subject to change based on projected budgets.
Navigation Menu
February-May 2025
Beginning Monday, February 24, the City of Palm Coast’s micro-surfacing contractor began crack sealing on multiple roadways as part of a pavement preservation project. This is a temporary step in the process, not the final road surface.
During this phase, the contractor cleaned and filled larger existing cracks in the roadway. Once the material was fully cured, crews returned in April to complete the micro-surfacing application on the entire roadway
The following roads were part of this process.
Ballard Lane, Ballenger Lane, Baltimore Lane, Barbera Lane, Barkley Lane, Barkwood Lane, Bassett Lane, Carr Lane, Cerrudo Lane, Collins Lane, Eastgate Lane, Eastman Lane, Eastmoor Lane, Fairbank Lane, Faircastle Lane, Fairmont Lane, Lancaster Lane, Lansdowne Lane, Louisburg Lane, Louvet Lane, Post Lane, Post Oak Lane, Post Tree Lane, Postman Lane, Rosecroft Lane, Rosepetal Lane, Royal Leaf Lane, Royal Palm Lane, Royal Tern Lane, Wood Center Lane, Wood Clift Lane, and Wood Crest Lane.



November 2024
Despite some minimal delays and complications in the wake of Hurricane Milton, crews were able to complete this project and complete a large portion of the work overnight to help mitigate potential traffic issues.

October 2024
With milling and resurfacing of the entirety of Pine Lakes Pkwy now complete, crews started work late last week on milling and resurfacing of Rymfire Drive. Crews will be on the road over the next several weeks and motorists can expect minimal delays while work is underway. Once completed, milling and resurfacing will commence on Royal Palms Pkwy.

May 2024
Microsurfacing efforts have been completed along the following streets throughout the month of May. These efforts were completed to assure quality is maintained along these roadways.
Fairhill Lane, Fairchild Lane, and Barley Lane, Bannbury Lane and Banner Lane, Woodward Lane, Woodworth Lane, Woodholme Lane, Woodhollow Lane, Rivera Lane, Ranshire Lane, Riviere Lane, Ranwood Lane, Riverina Lane, Ranch Way, Porpoise Lane, Porwyn Lane, Pillary Lane, Pilgrim Drive, Pleasant Lane, Plumtree Place, Plateau Place, Plateau Lane, Pillar Lane and Plainview Drive
Similar microsurfacing efforts may take place at other locations in the future on as needed basis.
