Colbert West Addition
The Colbert Lane West Addition Project is part of the Old B-Section Stormwater Conveyance Improvements and focuses on upgrading aging drainage infrastructure that carries stormwater toward Graham Swamp.
Navigation Menu
February 2026
Major underground and roadway preparation work is now complete. Sidewalk demolition, curb removal, utility directional drilling, and water main tie-ins have all been finished. Crews also completed Phase 1 of temporary lane and shoulder paving, along with the installation of barrier walls to safely maintain traffic flow.
With these foundational elements in place, the Colbert Lane West project is progressing as planned and moving into the next phase of construction. As always, thank you for your patience as this important infrastructure improvement continues.
January 2026
Work on the Old B Section Stormwater Conveyance Improvements project continued in January with preparation for replacement of the existing drainage infrastructure that carries stormwater toward Graham Swamp. This project will remove four (4) 72-inch reinforced concrete pipes (RCPs) and replace them with four (4) 7’ x 12’ concrete box culverts, increasing stormwater conveyance capacity and helping move water out of the area more quickly during heavy rain events. Additional updates will be posted as construction activities progress and major milestones are reached.
