Colbert West Addition

The Colbert Lane West Addition Project is part of the Old B-Section Stormwater Conveyance Improvements and focuses on upgrading aging drainage infrastructure that carries stormwater toward Graham Swamp.

Palm Coast Progress graphic that says Progress with the Palm Coast Logo featured.

Image Description
The Colbert Lane West Addition Project is part of the Old B-Section Stormwater Conveyance Improvements and focuses on upgrading aging drainage infrastructure that carries stormwater toward Graham Swamp.

February 2026

Major underground and roadway preparation work is now complete. Sidewalk demolition, curb removal, utility directional drilling, and water main tie-ins have all been finished. Crews also completed Phase 1 of temporary lane and shoulder paving, along with the installation of barrier walls to safely maintain traffic flow.

With these foundational elements in place, the Colbert Lane West project is progressing as planned and moving into the next phase of construction. As always, thank you for your patience as this important infrastructure improvement continues.

e4dd0216-43ab-4986-b04c-0742fbb78898 (1).jpg TC_00812 (002).JPG


January 2026

Work on the Old B Section Stormwater Conveyance Improvements project continued in January with preparation for replacement of the existing drainage infrastructure that carries stormwater toward Graham Swamp. This project will remove four (4) 72-inch reinforced concrete pipes (RCPs) and replace them with four (4) 7’ x 12’ concrete box culverts, increasing stormwater conveyance capacity and helping move water out of the area more quickly during heavy rain events. Additional updates will be posted as construction activities progress and major milestones are reached.

Colbert West Addition January 2026 Colbert West Addition January 2026