cleared land for the maintenance operations center

Maintenance Operations Center

The City of Palm Coast is building a new Maintenance Operations Center to strengthen fleet and field operations citywide. Phase 1 includes a Fleet Maintenance Building, Fueling Station, and Wash Building, supporting day-to-day maintenance needs and improving service efficiency for residents.

Image Description

cleared land for the maintenance operations center
Maintenance Operations Center
The Maintenance Operations Center is part of a multi-phase master plan designed to improve operational capacity for City maintenance and fleet services. Phase 1 focuses on core infrastructure and facilities, including major underground utility work, stormwater systems, and site development needed to support the Fleet Maintenance Building, Fueling Station, and Wash Building. Future phases may include an Admin/Operations Facility and roadway improvements to Peavy Grade. This project is targeting LEED Silver Certification.

March 2026

Construction progress continues on the new maintenance operations center, including near completion of sitework development, and starting of initial work on the new fuel depot.

 

  


January 2026

Significant progress is underway on construction at the City of Palm Coast's new Maintenance Operations Complex. Curbing across the site was recently installed, with the definitive outline of the facility beginning to take shape.

    

 


AUGUST 2025

Strong progress continued on Phase 1 in August, with substantial work completed on underground utilities and storm structures. Full completion of this utility phase is expected by late September. Crews also stabilized and sodded pond buffers and banks for erosion control. Maintaining SWPPP compliance (stormwater pollution prevention requirements) has been challenging due to heavy rainfall, but stabilization efforts remain ongoing. Electrical crews began mobilizing in early September, with pole installation anticipated by mid-month. The project remains on track and continues targeting LEED Silver Certification.

Link to Site Development Video

   

 


July 2025

Significant progress was made in July with utility installation across the site. Crews installed water mains along the western road and continued coordinated work on utilities and underground storm drains. All pressure piping, including reuse, potable water, and force main, was installed up to the end of Lake 1C. Work also began on the first run of the gravity sewer line, and banks were stabilized to help prevent washouts. Preparations continued for electrical mobilization to install underground electric, low-voltage conduits, and precast light poles.

   

 


June 2025

Phase 1 site work advanced in June with procurement of major underground utility and storm system materials, including PVC piping, precast structures, and hydrants. Wet taps were completed at utility mains along Peavy Grade, and planning began for routing reuse and force main lines across the roadway. Coordination for FPL power and conduit routing was finalized, and TECO feasibility was approved. Despite rainy season impacts, additional pipe crews are being brought in to maintain progress. The City’s construction manager also began bidding Phase 1B, with strong contractor participation. The project continues targeting LEED Silver Certification.

Link to Site Development Video

   

 


May 2025

In May, crews completed importing soils, including the final lift that was originally planned as limerock but was value engineered for substantial cost savings. Materials delivered throughout the month included precast structures, PVC pipe for underground utilities, FPL conduits and transformer pad, and precast poles for lighting and CCTV infrastructure.